Security of Payment in Victoria: the deadlines a subcontractor works to
Every date below comes from the Building and Construction Industry Security of Payment Act 2002 (VIC), as amended by Act 43/2025 (in force 15 Apr 2026), and each one shows the section it comes from so you can check it. The contract can set an earlier date than the Act in places, and the Act wins where the contract is later than it allows.
For the actual dates on your claim, put the day you served it into the deadline calculator.
How long does the builder have to answer a payment claim in Victoria?
Miss this and the respondent becomes liable for the FULL claimed amount on the due date, recoverable as a debt or via adjudication, with no contract defences in debt proceedings.
VIC s 15(4)(b)
When does a subcontractor's payment fall due in Victoria?
VIC s 12(1)
What can a subcontractor do in Victoria if no payment schedule comes back?
Without this notice the no-schedule adjudication path is barred.
VIC s 18(2)-(2A)
How long does a subcontractor have to apply for adjudication in Victoria?
Apply late and the adjudication right for this claim is lost.
VIC s 18(3)(c)
Apply late and the adjudication right for this claim is lost.
VIC s 18(3)(d)
Apply late and the adjudication right for this claim is lost.
VIC s 18(3)(e)
Which days are not business days under the Security of Payment Act in Victoria?
Weekends and public holidays, and the Act itself takes out 22 December to 31 December (VIC s 4(1)), 1 January to 10 January (VIC s 4(1)).
Not legal advice. These are statutory defaults. Verify every date against the relevant Security of Payment Act and your contract.
Business-day counting excludes weekends, the Act-specific December/January shutdown, New Year’s Day, Australia Day, Good Friday, Easter Monday, Anzac Day, Christmas Day and Boxing Day, plus the substitute weekday where New Year’s Day, Australia Day, Christmas Day or Boxing Day falls on a weekend. Anzac Day is substituted in Queensland when 25 April falls on a Sunday, as it is in the Australian Capital Territory and the Northern Territory, and in Western Australia when it falls on either a Saturday or a Sunday. State and territory public holidays are modelled for New South Wales, Queensland, Victoria, Western Australia, South Australia, Tasmania, the Australian Capital Territory and the Northern Territory. State public holidays counted here: Labour Day, King’s Birthday, Melbourne Cup Day, Easter Saturday, Easter Sunday, Friday before the AFL Grand Final. The rules fixing those dates were taken from secondary sources rather than read off a government page, so check them against the published holiday list before you rely on a date. Friday before the AFL Grand Final is counted only up to 2026, because it is appointed by order each year rather than fixed by a rule, and the published dates run only to 2026. A count that reaches a later late September or October can fall one business day earlier than it should.
On a real job, you do not type any of this
YourCA reads your head contract, works out the dates it puts on you and warns you before each one closes: claim day three days out, a variation notice window two days before it shuts, their payment schedule the day it is late. Every figure shows the clause it came from.