How do I raise an RFI?
- Open RFIs on the Documents tab. Press Raise an RFI at the right of the section band.
- The form has two actions. Raise it asks the builder immediately. Save as a draft keeps the question here and asks nobody.
- On a phone, the plus in the middle of the bar at the bottom of the screen opens the same form from anywhere. Choose A question for the builder.
- This matters on site. The clock should start the moment you know you are blocked.
- A draft is under Drafts on the register, with two things to press.
- Correct it opens the same form again, and you can change every word. Issue it actually asks the question.
- When you issue it, editing stops. The builder holds a copy. So a correction after issue raises a revision that refers to the original. It does not rewrite it.
- Set a required by date. If an RFI has no answer after that date, YourCA puts a delay event in your diary, with the RFI as its source.
- Each question is one line. It shows the two dates, the status, and at the end the action that writes to the record.
- Press the line to open it. It shows the full question, and if a late answer has a cost or a time result.
- It also shows the answer when it comes, the papers on each side, and the chase drafted for you to send from your own email.
- When the answer comes, record it.
- Then close it out on the day you actually accept it. That is often not the day it arrived.
- Export, in the open line, asks PDF or Word. It builds the question as a document on your own letterhead.
- The document has your business name and logo, your job number and theirs, the question, every date the register holds, and a line that asks them to quote the number in their reply.
- The PDF opens for you to print or save. You send it yourself.
- A draft has no Export, because a letterhead on a question nobody was asked says it went out.
Worth knowing
A delay argument is built from the turnaround pair: the date it went and the date they answered.